Progress billing for construction in the Philippines: accomplishment, retention and variations
How Philippine contractors run progress billing: statements of work accomplished, retention and its release, variation orders and the new procurement law.
Published by Data Reach Solutions on . Last checked against the sources below on . 9 minute read.

Progress billing for construction in the Philippines follows one chain. The site records what was built, the contractor prices it in a statement of work accomplished (SWA), and the owner certifies it and pays it less earlier payments, recoupment and retention. Private contracts on CIAP Document 102 terms and government contracts under the IRR of RA 12009 both retain 10% of each billing until half the work is done (on government jobs, longer if the work falls behind).
This is general information, not legal, tax or procurement advice, based on documents we read as of 22 November 2026. Your signed contract governs, so check its terms with your lawyer, accountant or the procuring entity.
How does progress billing for construction in the Philippines work?
Each billing cycle turns measured site work into cash in five steps, and a delay at any step delays payment.
CIAP Document 102 is the uniform general conditions for private construction. As CIAP’s FAQs on Document 102 summarise it, the contractor bills at most monthly, and the owner must certify and pay within 30 days, with interest if late (Articles 22.02 and 22.05). On government work, Section 71.2.7 of the IRR of RA 12009 makes the SWA monthly unless the procuring entity requires, in the bidding documents, billing only on completion or at set milestones.
- Site accomplishment: engineers measure installed quantities per bill of quantities item, with photos and inspection records.
- Statement of work accomplished: quantities are priced at contract rates, cumulative to date, plus approved variation orders.
- Certification: the owner’s representative or project engineer checks the SWA and certifies the amount.
- Deductions and payment: earlier payments, recoupment, retention and other deductions come off, and the net is paid.
- Retention ledger: amounts held back are tracked per project until release.
What is a statement of work accomplished?
A statement of work accomplished is the contractor’s claim for the cumulative value of work done to date, line by line against the bill of quantities, plus approved variation orders (IRR Section 71.2.7). Every progress billing is built on it.
In private work, unless the contract pays by unit prices, CIAP Document 102 asks for a breakdown of work and corresponding value within 15 days of the notice to proceed or the start of work, and that breakdown becomes the basis of every request for payment (Article 22.01).
A progress billing format that holds up in review has these columns for each line:
- Item number and description, exactly as in the bill of quantities.
- Unit, contract quantity, unit price and contract amount.
- Quantity and amount: previous, this period and to date.
- Percentage complete for the item and for the contract.
- A reference to the evidence: measurement sheet, photos, test results, inspection report.
Keep that evidence: CIAP notes that approval of a billing is provisional, and the owner may re-measure and downgrade an earlier accomplishment. Both forms exclude materials delivered but not yet installed, unless the contract says otherwise. CIAP adds one exception, where shortages or transport problems forced an early purchase and the contractor submits bills of sale (Article 22.02).
How is a progress billing computed?
Take the cumulative value of work to date, subtract what was certified before, then deduct recoupment, retention and other contract deductions. Working from cumulative figures stops one billing’s error from carrying into the next.
For illustration, this sample uses an invented private contract of PHP 12,000,000 on CIAP Document 102 retention terms, with a 15% downpayment recouped at 15% of each billing. Billing no. 3 brings the work to 58% of the original scope, plus PHP 140,000 of approved variation order work.
| Line | How it is worked out | Amount |
|---|---|---|
| A. Original scope done to date | 58% of PHP 12,000,000 | PHP 6,960,000 |
| B. Approved variation order work | From the variation order register | PHP 140,000 |
| C. Gross value to date | A + B | PHP 7,100,000 |
| D. Less: previously certified | Billings 1 and 2, 40% of the contract | PHP 4,800,000 |
| E. Gross value this billing | C minus D | PHP 2,300,000 |
| F. Less: downpayment recoupment | 15% of E | PHP 345,000 |
| G. Less: retention | 10% of the PHP 1,200,000 still below the 50% mark | PHP 120,000 |
| H. Net amount due | E minus F minus G | PHP 1,835,000 |
This sample assumes retention is prorated at the 50% mark and that the 50% is measured on the original contract price. Some owners retain on the whole billing that crosses the mark, or on variation order work, so check your contract. On the sample’s reading, retention now stops, and the ledger holds PHP 600,000, or 5% of the contract price.
Other deductions can apply: the cost of uncorrected defects (IRR Section 71.2.7; CIAP Article 22.03) and liquidated damages (IRR Section 71.2.4; CIAP Article 22.03). The sample also leaves out tax. Whether the contract price includes VAT, and what tax the owner withholds from each payment, depends on your contract and the owner; agree the treatment with your accountant.
How much retention is held, and when is it released?
Retention, sometimes called a retention fee, normally tops out at 5% of the contract price, because both forms hold 10% of each billing until 50% of the work is done. It comes back after completion: against a guarantee bond in private work, on final acceptance in government work.
Private contracts. CIAP Document 102 stops retention once 50% of the contract is accomplished (Article 22.02). Substantial completion is 95% of the work (Article 20.11). CIAP’s table of time limits puts release at not later than 60 days from substantial completion, once the contractor posts a one-year guarantee bond equal to the retention released (Article 22.11). The article’s own wording ties release to the end of the period for correcting punch list items, which can run past 60 days, and CIAP calls that wording ambiguous, so write the release date into your contract.
Government contracts. Section 71.2.8 of the IRR sets retention at 10% of the amount due before deductions, until 50% of the works are complete. After that, nothing more is retained if the work is satisfactory and on schedule; otherwise the 10% continues, which the procuring entity may reduce to 5% for justifiable causes. Release is on final acceptance, and Section 90.2.2 describes the defects liability period as one year from completion up to final acceptance, so the money can stay out for a year or more.
If the project is on schedule and the work satisfactory, a government contractor may ask to swap each billing’s retention for a standby letter of credit, bank guarantee or surety bond callable on demand. A late project can also lose part of its retention: on government jobs, liquidated damages can be collected from it (Section 71.2.4), and CIAP Document 102 lets a private owner deduct them from any payment due (Article 22.03).
How are variation orders billed?
Bill a variation order only after written approval, at the agreed prices, as a separate block in the SWA. Work done without approval risks never being paid.
Government contracts. Section 71.2.1 of the IRR splits variation orders into change orders, for more or less of an original item, and extra work orders, for new items. Positive variation orders may total 10% of the original contract price, or 20% in exceptional cases the head of the procuring entity approves. Change orders use the original unit prices; extra work orders use the original direct unit costs plus the bid mark-up. Work may start before approval only in emergencies or when time is of the essence, and only up to 5% of the adjusted original contract price in unapproved work. Payment waits for approval.
Private contracts. Article 20.07 of CIAP Document 102 lets the owner order changes in writing up to an aggregate 25% of the original contract price; larger overruns need a supplemental contract. Extra work is valued by lump sum, unit prices, or actual direct cost plus VAT, if any, plus 15% for overhead and profit. A claim for extra cost is due within 15 days of receiving the instruction (Article 20.08).
What changed for government contracts under RA 12009?
The law changed, but the billing arithmetic mostly carried over from RA 9184. Check which law covers your project and what COA expects.
RA 12009, the New Government Procurement Act, took effect on 13 August 2024, and its IRR on 25 February 2025. GPPB Circular No. 01-2025 keeps RA 9184 and its IRR for projects published before 25 February 2025, made the new Philippine Bidding Documents mandatory on 21 September 2025, and gives agencies until 15 May 2028 to comply fully.
Monthly SWAs, 10% retention until 50% completion, release on final acceptance, the 10% variation order cap and the right to suspend work when complete billings stay unpaid beyond 45 calendar days appear in both Annex E of the 2016 IRR of RA 9184 and the new IRR. The clear change: agencies may now reduce continuing retention to 5%.
For progress payments, COA Circular No. 2023-004 lists the SWA, the billing statement, the agency engineer’s inspection report, test results where applicable, the contractor’s affidavit on payment of labourers and materials, geotagged photos before, during and after construction, and a certificate of percentage of completion. Release of retention needs a warranty security and the end user’s certificate of completion and acceptance.
Where do spreadsheets fail, and what should you automate?
Spreadsheets fail at the joins: between site quantities and the SWA, between billings, and between billing and the retention ledger. Automate the arithmetic and reminders; keep people on measurement and approval.
- The previous column is retyped instead of carried forward, so cumulative totals drift.
- Retention is still deducted after the 50% mark when the contract says it should stop.
- Advance recoupment is not tracked down to zero.
- Variation order work is billed before approval, then rejected.
- Photos sit in group chats, not linked to bill of quantities lines.
- Retention release dates and bond expiries are lost when the project team moves on.
A sound setup keeps one bill of quantities per project, links photos to each line, builds the SWA from cumulative figures, applies the deductions automatically and keeps a retention ledger with reminders. A project dashboard then shows billed, paid and retained amounts.
The certified billing becomes an invoice. Since the EOPT Act, the Bureau of Internal Revenue (BIR) recognises VAT on services, including sales to government, on billing rather than collection (RR 3-2024), so invoice timing matters; see our BIR e-invoicing checklist. Data Reach Solutions builds systems that connect site reports to finance and billing for contractors.
What to do next
Start with the billings you already have.
- Check your last three billings against the contract: retention rate, the 50% cap, recoupment and deductions.
- Start a retention ledger per project: amount held, release trigger, expected date and bond expiry.
- For government projects, confirm whether RA 9184 or RA 12009 applies, and prepare the COA attachments monthly.
Common questions
What is a statement of work accomplished?
It is the contractor’s periodic claim for the cumulative value of work done to date, against the bill of quantities, plus approved variation orders. The owner’s engineer checks it and certifies the amount payable, and on government projects COA requires it with every progress payment.
How much retention is usual in private construction?
CIAP Document 102, the standard general conditions for private construction, sets 10% of each progress payment until 50% of the contract is accomplished, which works out to 5% of the contract price. Your contract can adopt those terms or set its own, so read the retention clause before you price the job.
When is retention released?
For private work on CIAP Document 102 terms, CIAP’s summary table says not later than 60 days from substantial completion, once the contractor posts a guarantee bond equal to the retention released; the article’s own wording is ambiguous, so put the date in your contract. Government retention under the IRR of RA 12009 is due on final acceptance, after the one-year defects liability period, and liquidated damages can be collected from it first.
Sources
- GPPB, Implementing Rules and Regulations of RA 12009, approved by GPPB Resolution No. 02-2025 (4 February 2025), Official Gazette copy (10 February 2025), Sections 71.2, 90 and 113
- GPPB, Resolution No. 02-2025 approving the IRR of RA 12009 (4 February 2025)
- GPPB, Circular No. 01-2025 on the transitory provision of RA 12009 (18 September 2025)
- GPPB, Public Advisory No. 09-2026 on the official IRR of RA 12009 (31 July 2026)
- Republic Act No. 12009, New Government Procurement Act (20 July 2024), via Lawphil
- GPPB, Updated 2016 Revised IRR of RA 9184, Annex E (as of 15 October 2023)
- Construction Industry Authority of the Philippines, FAQs on CIAP Document 102, Uniform General Conditions of Contract for Private Construction
- Commission on Audit, Circular No. 2023-004, updated documentary requirements for common government transactions (14 June 2023), copy hosted by UP Manila
- BIR, Revenue Regulations No. 3-2024 digest, VAT and percentage tax under the EOPT Act (11 April 2024)